  • 08.04.2022
  • 3851
Launch of the request for qualification for 200 MW wind project in Karakalpakstan region of the Republic of Uzbekistan with support from EBRD

The Government of the Republic of Uzbekistan (GOU) is implementing a large-scale renewable energy strategy to deploy 12 GW of cost effective and environment-friendly renewable energy generation by 2030 to the increasing energy demand across the country. Under this initiative, the GOU has signed a memorandum of understanding with the European Bank for Reconstruction and Development (EBRD) to cooperate on the development of large-scale wind power projects up to a total capacity of 1,000 MW (Wind Program). GOU has successfully awarded the first project under the Wind Program with a capacity of 100 MW in October 2021.

  • 04.04.2022
  • 953
List of prequalified bidders for 3 Solar PV plants in Uzbekistan, in tender conducted with IFC

Tashkent, Uzbekistan, 30 March 2022 – In response to the request for qualifications (RFQ) for the Uzbek Solar 3 Project (total 500 MW at 3 sites in Bukhara, Namangan and Khorezm) published on August 30, 2021, the Ministry of Energy of the Republic of Uzbekistan has received 15 RFQ Applications before the deadline of November 29, 2021, 23:00 hours Tashkent Time.

  • 04.04.2022
  • 1073
Investment project "Construction of 125 km of 500 kV Sarimay - Dzhankeldy high voltage transmission line"

The project is implemented on the basis of the following resolutions of the President of the Republic of Uzbekistan: - Resolution No. PP-5001 of February 28, 2021 "On measures to implement the investment project" Construction of a wind power plant with a capacity of 300-500 MW in Peshku district of Bukhara region" - Resolution No. PQ-5003 of February 23, 2021 "On measures to implement the investment project" Construction of a wind power plant with a capacity of 500 MW in Gidjuvan district of Bukhara region " in accordance with the Resolution of the Government of the Republic of Uzbekistan dated December 30, 2021 No. PP-72 "On approval of the Investment Program of the Republic of Uzbekistan for 2022-2026 and the introduction of new approaches and mechanisms for managing investment projects"

  • 16.03.2022
  • 1803
Ernst & Young has provided a positive audit opinion on the financial statements of National Electricity Grids of Uzbekistan JSC for 2019–2020

Information on the international audit of consolidated (consolidated) financial statements prepared in accordance with the requirements of IFRS for 2019-2020, Department for the implementation of international financial reporting standards of JSC «National Electric Grids of Uzbekistan».

  • 24.01.2022
  • 1589
Joint Stock Company “National Electrical Grid of Uzbekistan” announces a competition for the selection of a Financial Management Specialist

Terms of Reference Financial Management Specialist at the Project Management Unit “Modernization and upgrade of transmission substations”

  • 09.12.2021
  • 889
Joint Stock Company “National Electrical Grid of Uzbekistan” announces a competition for the selection of a social specialist

The Social Specialist suitable for this position should have the following qualifications:

  • 09.12.2021
  • 854
Electricity Sector Transformation and Resilient Transmission - ESTART (P171683) Terms of Reference Social Specialist at the Project Management Unit

Joint Stock Company “National Electrical Grid of Uzbekistan” The Government of Uzbekistan has confirmed that energy sector reforms should remain the main and most important development priority, considering its role and contribution to the country’s economy.

  • 29.11.2021
  • 1793
Terms of Reference Financial Management Specialist at the Project Management Unit “Modernization and upgrade of transmission substations” Joint Stock Company “National Electrical Grid of Uzbekistan”

The Government of Uzbekistan has confirmed that energy sector reforms should remain the main and most important development priority, taking into account its role and contribution to the country’s economy.

  • 29.11.2021
  • 1146
Results for Contracts Awarded on Procurement of reinforced concrete products on Lot No. 7/2/3 Project Name: Modernization and upgrade of transmission substations

Project Number: MUTS/ICB/2016 Funding source: World Bank Project Name: Modernization and upgrade of transmission substations Package No: MUTS/ICB/2016-7/2 Lot No.: MUTS/ICB/2016-7/2/3 Evaluation Currency: USD Procurement Method: International Competitive Bidding (ICB) Procurement Type: Goods

  • 05.11.2021
  • 1159
Results for Contracts Awarded on Procurement of metal products on Lot No. 7/2/2 Project Name: Modernization and upgrade of transmission substations

Project Number: MUTS/ICB/2016 Funding source: World Bank Project Name: Modernization and upgrade of transmission substations Package No: MUTS/ICB/2016-7/2 Lot No.: MUTS/ICB/2016-7/2/2 Evaluation Currency: USD Procurement Method: International Competitive Bidding (ICB) Procurement Type: Goods

  • 05.11.2021
  • 1077
Results for Contracts Awarded on Procurement of cables and wires, buses and cable structures on Lot No. 7/2/1 Project Name: Modernization and upgrade of transmission substations.

Project Number: MUTS/ICB/2016 Funding source: World Bank Project Name: Modernization and upgrade of transmission substations Package No: MUTS/ICB/2016-7/2 Lot No.: MUTS/ICB/2016-7/2/1 Evaluation Currency: USD Procurement Method: International Competitive Bidding (ICB) Procurement Type: Goods

  • 05.11.2021
  • 1447
Uzbekistan: Partial Credit Guarantee Facility for Uzbekistan Solar PPP Program

Land Acquisition and Resettlement Framework prepared by JSC National Electric Grid of Uzbekistan for the Asian Development Bank

  • 16.07.2021
  • 997
Online resume

  • 07.05.2021
  • 739
Results for Contracts Awarded on Procurement of line coupling fittings and insulators on Lot No. 7/1

Project Name: Modernization and upgrade of transmission substations. Project Number: MUTS/ICB/2016

  • 22.04.2021
  • 1160