Information for 2019–2024 is available at this link    arxiv.uzbekistonmet.uz
Projects
Land Acquisition and Resettlement Plan Prepared under the World Bank Project
  • 07.07.2026
  • 8

Land Acquisition and Resettlement Plan Prepared under the World Bank Project

⇒ Pursuant to the Resolution of the President of the Republic of Uzbekistan No. PP-4791 dated 29 July 2020, “On Measures to Further Improve the Reliability of Electricity Supply in Tashkent City and Tashkent Region,” the investment project “Construction of the New 500 kV Halqa Substation and 220 kV and 500 kV Overhead Transmission Lines” is being implemented with financing from the World Bank.

In accordance with the World Bank’s environmental and social requirements, the Land Acquisition and Resettlement Plan (LARP) was prepared and translated into the Uzbek language.

► Brief Information about the Project:

Within the framework of the investment project “Construction of the New 500 kV Halqa Substation and 220 kV and 500 kV Overhead Transmission Lines,” the construction of a 220 kV overhead transmission line is being carried out. As part of this component, an 88.5 km transmission line is under construction in the Kuyi Chirchik District of the Tashkent Region.

✍️ Azizbek Botirov
Head of the Department for Environmental, Social and Land Relations JSC “National Electric Grid of Uzbekistan” (NEGU)

Information service of JSC «National Electric Grid of Uzbekistan» 

http://t.me/uzmetaxborotxizmati