JSC "National Electric Grid of Uzbekistan" within the framework of implementation of investment projects "Construction of the 500/220 kV Muruntau transmission substation and of 220 kV line in the size of 500 kV from the Navoi TPP to the 220 kV 'Besopan' switching station" with consideration of proposals received from interested companies, taking part in the bidding process, according to the approval of the European Bank for Reconstruction and Development (dated March 31, 2021) and the Procurement Committee minutes the bidding submission period was prolonged from April 5 till May 6, 2021.
Information service of JSC «NEG of Uzbekistan»